Demolition of Former Ellinwood Hospital Building Scheduled Following After Harvest Festival
ELLINWOOD, Kan. — Demolition work on the former hospital building in Ellinwood is scheduled to begin July 20, immediately following the conclusion of the After Harvest Festival weekend. Prior to demolition, asbestos abatement work is expected to begin this week as part of the site preparation process. The demolition project will be completed by Eakin Construction of Larned and is anticipated to take approximately 7–8 business days to complete. While the building itself will b